Mumbai Metro Line 5 (planned)

Balkum Naka to APMC Kalyan: planned stations, the line's design plan and where it is planned to link up.

Line 5 is not open. No opening date is given on this site until one is announced. It is not in the route planner.

Planned stations

Balkum Naka to APMC Kalyan: 14 stations in the current station list. Names may change before opening.

The DPR plans Line 5 from Kapurbawdi (on Line 4) to Kalyan; the station markers run from Balkum Naka to APMC Kalyan. The list follows the markers.

  1. 1Balkum Naka
  2. 2Kasheli
  3. 3Kalhar
  4. 4Purna
  5. 5Anjurphata
  6. 6Dhamankar Naka
  7. 7Bhiwandi
  8. 8Gopal Nagar
  9. 9Temghar
  10. 10Rajnouli Village
  11. 11Gove Gaon MIDC
  12. 12Kon Gaon
  13. 13Kalyan · also Line 12
  14. 14APMC Kalyan

Map (approximate)

Balkum NakaAPMC KalyanKalyanKasheliKalharPurnaAnjurphataDhamankar NakaBhiwandiRajnouli Village

Approximate map: the stations are placed by their planned station markers and joined by straight lines, so this is not the track or a final alignment. A ring marks a station open today.

From the Detailed Project Report

Design figures from the September 2016 Detailed Project Report (Thane – Bhiwandi – Kalyan). The line as built can differ: the report's station count and the current station list do not always match.

Planned length
24.9 kmin the September 2016 DPR
Planned stations
17elevated
Depot
Not given here

Route

Thane (Kapurbawdi), Bhiwandi and Kalyan.

What this means today

This page follows the station markers rather than the plan's starting point. No opening date is recorded, and the planner does not route journeys on it.

Questions

Is Mumbai Metro Line 5 open?

No. No opening date is given on this site until one is announced. The route planner does not include it.

What are the stations on Mumbai Metro Line 5?

Line 5 is planned from Balkum Naka to APMC Kalyan with 14 stations in the current station list: Balkum Naka, Kasheli, Kalhar, Purna, Anjurphata, Dhamankar Naka, Bhiwandi, Gopal Nagar, Temghar, Rajnouli Village, Gove Gaon MIDC, Kon Gaon, Kalyan and APMC Kalyan. Names may change before opening.

How long is Mumbai Metro Line 5?

The September 2016 Detailed Project Report gives 24.9 km and 17 stations (elevated). These are design figures and may change as the line is built.