Mumbai Metro Line 10 (planned)
Gaimukh Reti Bandar to Shivaji Chowk (Mira Road): planned stations, the line's design plan and where it is planned to link up.
Line 10 is not open. No opening date is given on this site until one is announced. It is not in the route planner.
Planned stations
Gaimukh Reti Bandar to Shivaji Chowk (Mira Road): 4 stations in the current station list. Names may change before opening.
The DPR starts Line 10 at Gaimukh Reti Bandar, near the end of Line 4A at Gaimukh, and ends at Shivaji Chowk (Mira Road). The station list follows the DPR; there are no station markers for it.
- 1Gaimukh Reti Bandar
- 2Varsova Char Phata
- 3Kashimira
- 4Shivaji Chowk (Mira Road)
Station order diagram (not to scale)
Schematic: the stations in order, evenly spaced. There are no station markers for this line, so it is not a map: it shows no positions, distances or track. A ring marks a station open today.
From the Detailed Project Report
Design figures from the March 2019 Detailed Project Report (Gaimukh to Shivaji Chowk (Mira Road)). The line as built can differ: the report's station count and the current station list do not always match.
- Planned length
- 9.209 kmin the March 2019 DPR
- Planned stations
- 48.414 km elevated, 0.68 km underground, 0.115 km at ground level; all four stations elevated
- Depot
- Not given here
Route
Continues the Line 4 and 4A corridor from Gaimukh to Mira Road.
What this means today
No opening date is recorded, and the planner does not route journeys on it.
Questions
Is Mumbai Metro Line 10 open?
No. No opening date is given on this site until one is announced. The route planner does not include it.
What are the stations on Mumbai Metro Line 10?
Line 10 is planned from Gaimukh Reti Bandar to Shivaji Chowk (Mira Road) with 4 stations in the current station list: Gaimukh Reti Bandar, Varsova Char Phata, Kashimira and Shivaji Chowk (Mira Road). Names may change before opening.
How long is Mumbai Metro Line 10?
The March 2019 Detailed Project Report gives 9.209 km and 4 stations (8.414 km elevated, 0.68 km underground, 0.115 km at ground level; all four stations elevated). These are design figures and may change as the line is built.