Mumbai Metro Line 4 (planned)

Wadala (Bhakti Park) to Kasarvadavali: planned stations, the line's design plan and where it is planned to link up.

Line 4 is not open. The first section (Gaimukh to Cadbury Junction, with Line 4A) is targeted for December 2026. It is not in the route planner.

Planned stations

Wadala (Bhakti Park) to Kasarvadavali: 30 stations in the current station list. Names may change before opening.

The station markers run from Bhakti Park (Wadala) to Kasarvadavli.

  1. 1Bhakti Park · also Line 11 (as Wadala (Bhakti Park))
  2. 2Wadala T.T.
  3. 3Anik Bus Stop
  4. 4Siddarth Nagar
  5. 5Garodia Nagar
  6. 6Pant Nagar
  7. 7Laxmi Nagar
  8. 8Shreyas Cinema
  9. 9Godrej Colony
  10. 10Vikhroli
  11. 11Surya Nagar
  12. 12Gandhi Nagar
  13. 13Naval Housing
  14. 14Bhandup Mahapalika
  15. 15Bhandup
  16. 16Shangrila
  17. 17Sonapur
  18. 18Mulund Fire Station
  19. 19Mulund Naka
  20. 20Teen Haath Naka
  21. 21RTO Thane
  22. 22Mahapalika Marg
  23. 23Cadbury Junction
  24. 24Majiwada
  25. 25Kapurbawdi · also Line 5 (DPR)
  26. 26Manpada
  27. 27Tikuji Wadi
  28. 28Dongaripada
  29. 29Vijay Garden
  30. 30Kasarvadavli · also Line 4A

Map (approximate)

Bhakti ParkKasarvadavliKapurbawdiAnik Bus StopSiddarth NagarGarodia NagarPant NagarLaxmi NagarShreyas CinemaVikhroliSurya NagarGandhi NagarNaval HousingBhandupShangrilaSonapurMulund NakaTeen Haath NakaRTO ThaneMahapalika MargCadbury JunctionMajiwadaManpadaTikuji WadiDongaripadaVijay Garden

Approximate map: the stations are placed by their planned station markers and joined by straight lines, so this is not the track or a final alignment. A ring marks a station open today.

From the Detailed Project Report

Design figures from the May 2016 Detailed Project Report (Wadala – Ghatkopar – Mulund – Thane – Kasarvadavali). The line as built can differ: the report's station count and the current station list do not always match.

Planned length
32.322 kmin the May 2016 DPR
Planned stations
32entirely elevated
Depot
Main depot near Kasarvadavali, stabling depot near Ghatkopar

Route

One corridor with Line 4A (Kasarvadavali to Gaimukh), Line 10 (Gaimukh to Mira Road) and Line 11 (Wadala to CSMT), as the DPRs for Lines 10 and 11 describe it.

What this means today

Line 4 forms one corridor with Lines 4A, 10 and 11. Until trains run, nothing on this page is a timetable, and the planner does not route journeys on it.

Questions

Is Mumbai Metro Line 4 open?

No. The first section (Gaimukh to Cadbury Junction, with Line 4A) is targeted for December 2026. The route planner does not include it.

What are the stations on Mumbai Metro Line 4?

Line 4 is planned from Wadala (Bhakti Park) to Kasarvadavali with 30 stations in the current station list: Bhakti Park, Wadala T.T., Anik Bus Stop, Siddarth Nagar, Garodia Nagar, Pant Nagar, Laxmi Nagar, Shreyas Cinema, Godrej Colony, Vikhroli, Surya Nagar, Gandhi Nagar, Naval Housing, Bhandup Mahapalika, Bhandup, Shangrila, Sonapur, Mulund Fire Station, Mulund Naka, Teen Haath Naka, RTO Thane, Mahapalika Marg, Cadbury Junction, Majiwada, Kapurbawdi, Manpada, Tikuji Wadi, Dongaripada, Vijay Garden and Kasarvadavli. Names may change before opening.

How long is Mumbai Metro Line 4?

The May 2016 Detailed Project Report gives 32.322 km and 32 stations (entirely elevated). These are design figures and may change as the line is built.