Bengaluru Metro: upcoming lines and the network to 2032

From 14 Nov 2026 Namma Metro runs 103.6 km with 88 stations on the Purple, Green, Yellow and Pink Lines. When Phases 2 and 3 are complete the approved network will be about 222 km.

The network through the years

103.6 km and 88 stations in service from 14 Nov 2026

MadavaraNelamangalaTumakuruChallaghattaBidadiSilk InstituteHarohalliDelta Electronics BommasandraAttibeleKR PuramBudigere CrossHoskoteKalena AgraharaBannerghattaJiganiAttibeleSarjapurDommasandraVarthur KodiKadugodi Tree ParkDoddajalaDevanahalliKadabagereTavarekere village (Magadi Rd)SarjapurIbbaluruKoramangalaDairy CircleKR CircleHebbalNS Palya–JP Nagar 4th PhaseJP NagarMysuru RoadSumanahalli CrossPeenyaHebbalKempapuraHosahalliSumanahalli CrossKadabagereSG PalyaDairy CircleLakkasandraLangford TownRashtriya Military SchoolMG RoadShivajinagarCantonmentPottery TownTannery RoadVenkateshpuraKadugundanahalliNagawaraCentral Silk BoardHSR LayoutAgaraIbbaluruBellandurKadubeesanahalliKodibeesanahalliMarathahalliISRODoddanekundiDRDO Sports ComplexSaraswathi NagarKR PuramKR PuramKasturinagaraHoramavuHRBR LayoutKalyan NagarHBR LayoutNagawaraVeerannapalyaKempapuraHebbalHebbalKodigehalliJakkur CrossYelahankaBagalur CrossBettahalasuruDoddajalaAirport CityKIAL TerminalsKalena AgraharaHulimavuBilekahalli–IIMBNS Palya–JP Nagar 4th PhaseJayadeva HospitalSG PalyaBaiyappanahalliSwami Vivekananda RoadIndiranagarHalasuruTrinityMG RoadMagadi RoadHosahalliVijayanagarAttiguppeDeepanjali NagarMysuru RoadMG RoadCubbon ParkDr. B.R. Ambedkar (Vidhana Soudha)Sir M. Visvesvaraya (Central College)MajesticCity Railway StationMagadi RoadMysuru RoadPantharapalya–NayandahalliRajarajeshwari NagarJnanabharathiPattanagereKengeri Bus TerminalKengeriKR PuramSingayyanapalyaGarudacharapalyaHoodiSeetharampalyaKundalahalliNallurhalliSri Sathya Sai HospitalPattandur AgraharaKadugodi Tree ParkHopefarm ChannasandraWhitefield (Kadugodi)BaiyappanahalliBenniganahalliKR PuramKengeriChallaghattaMantri Square Sampige RoadSrirampuraMahakavi Kuvempu RoadRajajinagarMahalakshmiSandal Soap FactoryYeshwanthpurGoraguntepalyaPeenyaPeenya IndustryPeenya IndustryJalahalliDasarahalliNagasandraMantri Square Sampige RoadMajesticChickpeteKR MarketNational CollegeLalbaghSouth End CircleJayanagarRV RoadBanashankariJP NagarYelachenahalliYelachenahalliKonanakunte CrossDoddakallasandraVajarahalliThalaghattapuraSilk InstituteNagasandraManjunathanagaraChikkabidarakalluMadavaraRV RoadRagiguddaJayadeva HospitalBTM LayoutCentral Silk BoardBommanahalliHongasandraKudlu GateSingasandraHosa RoadBeratena AgraharaElectronic CityInfosys Foundation Konappana AgraharaHuskur RoadBiocon HebbagodiDelta Electronics BommasandraWhitefieldChallaghattaSilk InstituteMadavaraRV RoadBommasandraKalena AgraharaNagawaraCentral Silk BoardKIAL TerminalsNS Palya–JP Nagar 4th PhaseKempapuraJP NagarMysuru RoadSumanahalli CrossPeenyaHebbalHosahalliKadabagereSarjapurIbbaluruKoramangalaDairy CircleTumakuruBidadiHarohalliAttibeleHoskoteKadugodi Tree ParkDevanahalliTavarekere villageMG RoadMajesticKR PuramJayadeva Hospital
  • Running
  • Projected (target met)
  • Under construction
  • Approved
  • Awaiting approval
  • Proposed
  • Interchange

Positions are approximate. For the Orange, Grey and Red Lines and the Phase 4 proposals only key stations are shown and the routes are indicative. Past years show when public service started; future years assume today's targets are met.

All lines at a glance

LineLengthStationsStatusOpening
Purple Line43.5 km37RunningFull line since Oct 2023
Green Line33.5 km32RunningFull line since Nov 2024
Yellow Line19.15 km16RunningAug 2025
Pink Line21.25 km18Elevated section opens 14 Nov 2026Underground: Mar–May 2027 (target)
Blue Line58.19 km30Under construction, trials startedMid-2027 to Mar 2028, in stages
Orange Line32.15 km22ApprovedMay 2031 (target)
Grey Line12.5 km9ApprovedMay 2031 (target)
Red Line36.6–37.8 km28Awaiting Union approvalNot fixed
Phase 4about 215 km8 corridorsProposedNot fixed

Pink LineKalena Agrahara to Nagawara

Route
Kalena Agrahara to Nagawara
Length
21.25 km
Stations
18 (6 elevated, 12 underground)
Status
Elevated section Kalena Agrahara to SG Palya (7.5 km, 6 stations): safety inspection passed on 28 Oct 2026, inaugurated on 13 Nov 2026, passenger trains from 6 am on 14 Nov 2026, every 8 minutes to start with. Underground section Dairy Circle to Nagawara (13.76 km, 12 stations): trial runs planned from Nov 2026.
Opening
Underground section: March to May 2027 (target)
Change to
Jayadeva Hospital (Yellow Line), MG Road (Purple Line), Nagawara (Blue Line), NS Palya–JP Nagar 4th Phase (Orange Line), Dairy Circle (Red Line, proposed)

Sections

  1. 14 Nov 2026Kalena Agrahara – SG Palya (elevated) 7.5 km, opening
  2. Mar–May 2027Dairy Circle – Nagawara (underground) 13.76 km, under construction

Stations in order

  1. 1Kalena Agraharaformerly Gottigere
  2. 2Hulimavu
  3. 3Bilekahalli–IIMBformerly IIMB
  4. 4NS Palya–JP Nagar 4th PhaseOrange Lineformerly JP Nagar 4th Phase
  5. 5Jayadeva HospitalYellow Line
  6. 6SG PalyaSuddugunte Palya, formerly Tavarekere, near BTM Layout
  7. 7Dairy CircleRed Line, proposed
  8. 8Lakkasandra
  9. 9Langford Town
  10. 10Rashtriya Military Schoolalso listed as National Military School
  11. 11MG RoadPurple Line
  12. 12Shivajinagar
  13. 13Cantonmentat Cantonment railway station
  14. 14Pottery Town
  15. 15Tannery Road
  16. 16Venkateshpura
  17. 17Kadugundanahallialso spelt Kadugondanahalli
  18. 18NagawaraBlue Line
  • The underground section will be the longest underground stretch on the network.
  • Earlier deadlines (2020, Dec 2025, May 2026 and Aug 2026) were missed, so treat the 2027 date as a target.

Pink Line: stations and trains

Blue LineCentral Silk Board to KIAL Terminals

Route
Central Silk Board to Kempegowda International Airport, along the Outer Ring Road and via Hebbal
Length
58.19 km
Stations
30 (13 in Phase 2A, 17 in Phase 2B)
Status
Under construction. Main-line trial runs started in Nov 2026, from Baiyappanahalli depot to KR Puram and Doddanekundi.
Opening
Silk Board to KR Puram: mid-2027 (about May 2027). Hebbal to Airport: Sep 2027. KR Puram to Hebbal: early 2028. Full line: Mar 2028 (targets)
Change to
Central Silk Board (Yellow Line), KR Puram (Purple Line), Nagawara (Pink Line), Hebbal (Orange and Red Lines), Kempapura (Orange Line), Ibbaluru (Red Line)

Sections

  1. Mid-2027Central Silk Board – KR Puram (Phase 2A) 19.75 km, under construction
  2. Early 2028KR Puram – Hebbal (Phase 2B) 11 km, under construction
  3. Sep 2027Hebbal – Airport (Phase 2B) 27.44 km, under construction

Stations in order

  1. 1Central Silk BoardYellow Line
  2. 2HSR Layout
  3. 3Agara
  4. 4IbbaluruRed Line
  5. 5Bellandur
  6. 6Kadubeesanahalli
  7. 7Kodibeesanahalli
  8. 8Marathahalli
  9. 9ISRO
  10. 10Doddanekundi
  11. 11DRDO Sports Complexlisted as Bagmane Developers – DRDO Sports Complex
  12. 12Saraswathi Nagar
  13. 13KR PuramPurple LineKrishnarajapura on the Purple Line
  14. 14Kasturinagara
  15. 15Horamavu
  16. 16HRBR Layout
  17. 17Kalyan Nagar
  18. 18HBR Layout
  19. 19NagawaraPink Line
  20. 20Veerannapalya
  21. 21KempapuraOrange Line
  22. 22HebbalOrange and Red Linesalso spelt Hebbala
  23. 23Kodigehalli
  24. 24Jakkur Cross
  25. 25Yelahanka
  26. 26Bagalur Cross
  27. 27Bettahalasuru
  28. 28Doddajala
  29. 29Airport City
  30. 30KIAL Terminals
  • Earlier targets of Jun 2026 and Dec 2026 for Silk Board to KR Puram slipped; treat the 2027–28 dates as targets, not commitments.
  • Section lengths are 19.75 km, 11 km and 27.44 km as stated by the state government.

Orange LineNS Palya–JP Nagar 4th Phase to Kempapura

Route
NS Palya–JP Nagar 4th Phase to Kempapura, along the western Outer Ring Road and via Hebbal
Length
32.15 km
Stations
22
Status
Approved by the Union Cabinet in Aug 2024. Loan agreement signed in Mar 2026. Land acquisition is in progress; main construction has not started.
Opening
May 2031 (target; the original target was 2029)
Change to
NS Palya–JP Nagar 4th Phase (Pink Line), JP Nagar (Green Line), Mysuru Road (Purple Line), Sumanahalli Cross (Grey Line), Peenya (Green Line), Hebbal (Blue and Red Lines), Kempapura (Blue Line)

Sections

  1. May 2031NS Palya–JP Nagar 4th Phase – Kempapura 32.15 km, approved

Key stations

  1. NS Palya–JP Nagar 4th PhasePink Line
  2. JP NagarGreen Line
  3. Mysuru RoadPurple Line
  4. Sumanahalli CrossGrey Line
  5. PeenyaGreen Line
  6. HebbalBlue and Red Lines
  7. KempapuraBlue Line

The full station list is still being finalised; these are the key stations and interchanges.

  • The road design was revised in Oct 2026 to about 10 km of double-decker (road and metro) plus flyovers, in place of the earlier 37 km double-decker plan.
  • Construction tenders for the southern packages are at bidding stage.

Grey LineHosahalli to Kadabagere

Route
Hosahalli to Kadabagere, along Magadi Road
Length
12.5 km
Stations
9
Status
Approved with Phase 3 in Aug 2024. A detailed design consultant was appointed in Mar 2025; construction has not started.
Opening
May 2031 (target, with Phase 3)
Change to
Hosahalli (Purple Line), Sumanahalli Cross (Orange Line)

Sections

  1. May 2031Hosahalli – Kadabagere 12.5 km, approved

Key stations

  1. HosahalliPurple Line
  2. Sumanahalli CrossOrange Line
  3. Kadabagere

The full station list is still being finalised; these are the key stations and interchanges.

  • Some sources call it the Silver Line.
  • A 6.6 km extension from Kadabagere to Tavarekere village on Magadi Road is at DPR stage. This is a different place from SG Palya (formerly Tavarekere) on the Pink Line.

Red LineSarjapur to Hebbal

Route
Sarjapur to Hebbal via Koramangala, Dairy Circle and KR Circle
Length
36.6 km (revised plan about 37.8 km), about 14.45 km underground
Stations
28 (17 elevated, 11 underground)
Status
Approved by the Karnataka cabinet on 6 Dec 2024. The revised project report is with the Union government, which has given no timeline for approval.
Opening
No date. About 5.5 years of construction after approval
Change to
Ibbaluru (Blue Line), Dairy Circle (Pink Line), KR Circle (Purple Line), Hebbal (Blue and Orange Lines)

Sections

  1. Not fixed — awaiting Union approvalSarjapur – Hebbal 36.59 km, awaiting approval

Key stations

  1. Sarjapur
  2. IbbaluruBlue Line
  3. Koramangala
  4. Dairy CirclePink Line
  5. KR CirclePurple Line
  6. HebbalBlue and Orange Lines

The full station list is still being finalised; these are the key stations and interchanges.

  • This is Phase 3A of Namma Metro.

Phase 4 proposals

Eight suburban extensions, about 215 km in all. None of these is approved or funded. The state is also backing RRTS corridors, which may replace some of the intercity metro proposals.

  • Madavara – Tumakuru59.9 km

    Extends the Green Line

    Feasibility study and DPR done

  • Kalena Agrahara – Kadugodi Tree Park69 km

    Extends the Pink Line

    Feasibility study in progress. Via Jigani, Attibele and Sarjapur Road; a branch to Anekal is proposed

  • Silk Institute – Harohalli21.7 km

    Extends the Green Line

    Feasibility study done

  • KR Puram – Hoskote16 km

    Extends the Purple Line

    Feasibility study done. Via Budigere Cross

  • Challaghatta – Bidadi15.6 km

    Extends the Purple Line

    Feasibility study done

  • Doddajala – Devanahalli13.6 km

    Extends the Blue Line

    Feasibility study done

  • Bommasandra – Attibele11 km

    Extends the Yellow Line

    Feasibility study done

  • Kadabagere – Tavarekere village (Magadi Road)6.6 km

    Extends the Grey Line

    DPR stage, to go to the Union government with the Red Line. 5 elevated stations; not SG Palya (formerly Tavarekere) on the Pink Line

Timeline: 2011 to the 2030s

  1. 20 Oct 2011Purple Line First metro: Baiyappanahalli – MG Road (6.7 km)
  2. 1 Mar 2014Green Line Sampige Road – Peenya Industry
  3. 1 May 2015Green Line Peenya Industry – Nagasandra
  4. 16 Nov 2015Purple Line Mysuru Road – Magadi Road
  5. 30 Apr 2016Purple Line Underground MG Road – Magadi Road; the east–west line is complete
  6. 18 Jun 2017Green Line Sampige Road – Yelachenahalli; Phase 1 complete (about 42 km)
  7. 15 Jan 2021Green Line Yelachenahalli – Silk Institute
  8. 30 Aug 2021Purple Line Mysuru Road – Kengeri
  9. 26 Mar 2023Purple Line KR Puram – Whitefield (Kadugodi)
  10. 9 Oct 2023Purple Line Baiyappanahalli – KR Puram and Kengeri – Challaghatta; Purple Line complete (43.5 km)
  11. 7 Nov 2024Green Line Nagasandra – Madavara; Green Line complete
  12. 11 Aug 2025Yellow Line Yellow Line RV Road – Bommasandra (19.15 km); network about 96 km
  13. 14 Nov 2026nowPink Line Pink Line elevated Kalena Agrahara – SG Palya (7.5 km, 6 stations); inaugurated 13 Nov. Network 103.6 km
  14. Mar–May 2027targetPink Line Pink Line underground Dairy Circle – Nagawara (13.76 km, 12 stations)
  15. Mid-2027targetBlue Line Blue Line Central Silk Board – KR Puram (19.75 km)
  16. Sep 2027targetBlue Line Blue Line Hebbal – Airport (27.44 km)
  17. Early 2028targetBlue Line Blue Line KR Puram – Hebbal (11 km); full Blue Line by Mar 2028
  18. May 2031targetOrange Line Phase 3: Orange (32.15 km) and Grey (12.5 km) Lines; approved network about 222 km
  19. Not fixednot fixedRed Line Phase 3A Red Line Sarjapur – Hebbal, awaiting Union approval
  20. Not fixednot fixedPhase 4 Phase 4: 8 suburban corridors (about 215 km) at feasibility or DPR stage

Questions about upcoming lines

When will the Bengaluru Metro Blue Line to the airport open?

The Blue Line opens in stages. Targets: Silk Board to KR Puram: mid-2027 (about May 2027). Hebbal to Airport: Sep 2027. KR Puram to Hebbal: early 2028. Full line: Mar 2028 (targets). It runs 58.19 km from Central Silk Board to the airport with 30 stations.

When will the Pink Line underground section open?

The underground section from Dairy Circle to Nagawara (13.76 km, 12 stations) has a target of March to May 2027. The elevated section from Kalena Agrahara to SG Palya carries passengers from 6 am on 14 Nov 2026.

Which Bengaluru Metro lines are being built?

The Pink Line underground section and the Blue Line are under construction. The Orange and Grey Lines are approved with a May 2031 target. The Red Line is awaiting Union approval, and the Phase 4 corridors are proposals.

How long will the Bengaluru Metro network be?

From 14 Nov 2026 Namma Metro runs 103.6 km with 88 stations on the Purple, Green, Yellow and Pink Lines. When Phases 2 and 3 are complete the approved network will be about 222 km. Phase 4 proposals would add about 213 km more.