Bengaluru Metro: upcoming lines and the network to 2032
From 14 Nov 2026 Namma Metro runs 103.6 km with 88 stations on the Purple, Green, Yellow and Pink Lines. When Phases 2 and 3 are complete the approved network will be about 222 km.
The network through the years
103.6 km and 88 stations in service from 14 Nov 2026
- Running
- Projected (target met)
- Under construction
- Approved
- Awaiting approval
- Proposed
- Interchange
Positions are approximate. For the Orange, Grey and Red Lines and the Phase 4 proposals only key stations are shown and the routes are indicative. Past years show when public service started; future years assume today's targets are met.
All lines at a glance
| Line | Length | Stations | Status | Opening |
|---|---|---|---|---|
| Purple Line | 43.5 km | 37 | Running | Full line since Oct 2023 |
| Green Line | 33.5 km | 32 | Running | Full line since Nov 2024 |
| Yellow Line | 19.15 km | 16 | Running | Aug 2025 |
| Pink Line | 21.25 km | 18 | Elevated section opens 14 Nov 2026 | Underground: Mar–May 2027 (target) |
| Blue Line | 58.19 km | 30 | Under construction, trials started | Mid-2027 to Mar 2028, in stages |
| Orange Line | 32.15 km | 22 | Approved | May 2031 (target) |
| Grey Line | 12.5 km | 9 | Approved | May 2031 (target) |
| Red Line | 36.6–37.8 km | 28 | Awaiting Union approval | Not fixed |
| Phase 4 | about 215 km | 8 corridors | Proposed | Not fixed |
Pink LineKalena Agrahara to Nagawara
- Route
- Kalena Agrahara to Nagawara
- Length
- 21.25 km
- Stations
- 18 (6 elevated, 12 underground)
- Status
- Elevated section Kalena Agrahara to SG Palya (7.5 km, 6 stations): safety inspection passed on 28 Oct 2026, inaugurated on 13 Nov 2026, passenger trains from 6 am on 14 Nov 2026, every 8 minutes to start with. Underground section Dairy Circle to Nagawara (13.76 km, 12 stations): trial runs planned from Nov 2026.
- Opening
- Underground section: March to May 2027 (target)
- Change to
- Jayadeva Hospital (Yellow Line), MG Road (Purple Line), Nagawara (Blue Line), NS Palya–JP Nagar 4th Phase (Orange Line), Dairy Circle (Red Line, proposed)
Sections
- 14 Nov 2026Kalena Agrahara – SG Palya (elevated) 7.5 km, opening
- Mar–May 2027Dairy Circle – Nagawara (underground) 13.76 km, under construction
Stations in order
- 1Kalena Agrahara
- 2Hulimavu
- 3Bilekahalli–IIMB
- 4NS Palya–JP Nagar 4th Phase
- 5Jayadeva Hospital
- 6SG Palya
- 7Dairy Circle
- 8Lakkasandra
- 9Langford Town
- 10Rashtriya Military School
- 11MG Road
- 12Shivajinagar
- 13Cantonment
- 14Pottery Town
- 15Tannery Road
- 16Venkateshpura
- 17Kadugundanahalli
- 18Nagawara
- The underground section will be the longest underground stretch on the network.
- Earlier deadlines (2020, Dec 2025, May 2026 and Aug 2026) were missed, so treat the 2027 date as a target.
Blue LineCentral Silk Board to KIAL Terminals
- Route
- Central Silk Board to Kempegowda International Airport, along the Outer Ring Road and via Hebbal
- Length
- 58.19 km
- Stations
- 30 (13 in Phase 2A, 17 in Phase 2B)
- Status
- Under construction. Main-line trial runs started in Nov 2026, from Baiyappanahalli depot to KR Puram and Doddanekundi.
- Opening
- Silk Board to KR Puram: mid-2027 (about May 2027). Hebbal to Airport: Sep 2027. KR Puram to Hebbal: early 2028. Full line: Mar 2028 (targets)
- Change to
- Central Silk Board (Yellow Line), KR Puram (Purple Line), Nagawara (Pink Line), Hebbal (Orange and Red Lines), Kempapura (Orange Line), Ibbaluru (Red Line)
Sections
- Mid-2027Central Silk Board – KR Puram (Phase 2A) 19.75 km, under construction
- Early 2028KR Puram – Hebbal (Phase 2B) 11 km, under construction
- Sep 2027Hebbal – Airport (Phase 2B) 27.44 km, under construction
Stations in order
- 1Central Silk Board
- 2HSR Layout
- 3Agara
- 4Ibbaluru
- 5Bellandur
- 6Kadubeesanahalli
- 7Kodibeesanahalli
- 8Marathahalli
- 9ISRO
- 10Doddanekundi
- 11DRDO Sports Complex
- 12Saraswathi Nagar
- 13KR Puram
- 14Kasturinagara
- 15Horamavu
- 16HRBR Layout
- 17Kalyan Nagar
- 18HBR Layout
- 19Nagawara
- 20Veerannapalya
- 21Kempapura
- 22Hebbal
- 23Kodigehalli
- 24Jakkur Cross
- 25Yelahanka
- 26Bagalur Cross
- 27Bettahalasuru
- 28Doddajala
- 29Airport City
- 30KIAL Terminals
- Earlier targets of Jun 2026 and Dec 2026 for Silk Board to KR Puram slipped; treat the 2027–28 dates as targets, not commitments.
- Section lengths are 19.75 km, 11 km and 27.44 km as stated by the state government.
Orange LineNS Palya–JP Nagar 4th Phase to Kempapura
- Route
- NS Palya–JP Nagar 4th Phase to Kempapura, along the western Outer Ring Road and via Hebbal
- Length
- 32.15 km
- Stations
- 22
- Status
- Approved by the Union Cabinet in Aug 2024. Loan agreement signed in Mar 2026. Land acquisition is in progress; main construction has not started.
- Opening
- May 2031 (target; the original target was 2029)
- Change to
- NS Palya–JP Nagar 4th Phase (Pink Line), JP Nagar (Green Line), Mysuru Road (Purple Line), Sumanahalli Cross (Grey Line), Peenya (Green Line), Hebbal (Blue and Red Lines), Kempapura (Blue Line)
Sections
- May 2031NS Palya–JP Nagar 4th Phase – Kempapura 32.15 km, approved
Key stations
- NS Palya–JP Nagar 4th Phase
- JP Nagar
- Mysuru Road
- Sumanahalli Cross
- Peenya
- Hebbal
- Kempapura
The full station list is still being finalised; these are the key stations and interchanges.
- The road design was revised in Oct 2026 to about 10 km of double-decker (road and metro) plus flyovers, in place of the earlier 37 km double-decker plan.
- Construction tenders for the southern packages are at bidding stage.
Grey LineHosahalli to Kadabagere
- Route
- Hosahalli to Kadabagere, along Magadi Road
- Length
- 12.5 km
- Stations
- 9
- Status
- Approved with Phase 3 in Aug 2024. A detailed design consultant was appointed in Mar 2025; construction has not started.
- Opening
- May 2031 (target, with Phase 3)
- Change to
- Hosahalli (Purple Line), Sumanahalli Cross (Orange Line)
Sections
- May 2031Hosahalli – Kadabagere 12.5 km, approved
Key stations
- Hosahalli
- Sumanahalli Cross
- Kadabagere
The full station list is still being finalised; these are the key stations and interchanges.
- Some sources call it the Silver Line.
- A 6.6 km extension from Kadabagere to Tavarekere village on Magadi Road is at DPR stage. This is a different place from SG Palya (formerly Tavarekere) on the Pink Line.
Red LineSarjapur to Hebbal
- Route
- Sarjapur to Hebbal via Koramangala, Dairy Circle and KR Circle
- Length
- 36.6 km (revised plan about 37.8 km), about 14.45 km underground
- Stations
- 28 (17 elevated, 11 underground)
- Status
- Approved by the Karnataka cabinet on 6 Dec 2024. The revised project report is with the Union government, which has given no timeline for approval.
- Opening
- No date. About 5.5 years of construction after approval
- Change to
- Ibbaluru (Blue Line), Dairy Circle (Pink Line), KR Circle (Purple Line), Hebbal (Blue and Orange Lines)
Sections
- Not fixed — awaiting Union approvalSarjapur – Hebbal 36.59 km, awaiting approval
Key stations
- Sarjapur
- Ibbaluru
- Koramangala
- Dairy Circle
- KR Circle
- Hebbal
The full station list is still being finalised; these are the key stations and interchanges.
- This is Phase 3A of Namma Metro.
Phase 4 proposals
Eight suburban extensions, about 215 km in all. None of these is approved or funded. The state is also backing RRTS corridors, which may replace some of the intercity metro proposals.
- Madavara – Tumakuru59.9 km
Extends the Green Line
Feasibility study and DPR done
- Kalena Agrahara – Kadugodi Tree Park69 km
Extends the Pink Line
Feasibility study in progress. Via Jigani, Attibele and Sarjapur Road; a branch to Anekal is proposed
- Silk Institute – Harohalli21.7 km
Extends the Green Line
Feasibility study done
- KR Puram – Hoskote16 km
Extends the Purple Line
Feasibility study done. Via Budigere Cross
- Challaghatta – Bidadi15.6 km
Extends the Purple Line
Feasibility study done
- Doddajala – Devanahalli13.6 km
Extends the Blue Line
Feasibility study done
- Bommasandra – Attibele11 km
Extends the Yellow Line
Feasibility study done
- Kadabagere – Tavarekere village (Magadi Road)6.6 km
Extends the Grey Line
DPR stage, to go to the Union government with the Red Line. 5 elevated stations; not SG Palya (formerly Tavarekere) on the Pink Line
Timeline: 2011 to the 2030s
- 20 Oct 2011Purple Line First metro: Baiyappanahalli – MG Road (6.7 km)
- 1 Mar 2014Green Line Sampige Road – Peenya Industry
- 1 May 2015Green Line Peenya Industry – Nagasandra
- 16 Nov 2015Purple Line Mysuru Road – Magadi Road
- 30 Apr 2016Purple Line Underground MG Road – Magadi Road; the east–west line is complete
- 18 Jun 2017Green Line Sampige Road – Yelachenahalli; Phase 1 complete (about 42 km)
- 15 Jan 2021Green Line Yelachenahalli – Silk Institute
- 30 Aug 2021Purple Line Mysuru Road – Kengeri
- 26 Mar 2023Purple Line KR Puram – Whitefield (Kadugodi)
- 9 Oct 2023Purple Line Baiyappanahalli – KR Puram and Kengeri – Challaghatta; Purple Line complete (43.5 km)
- 7 Nov 2024Green Line Nagasandra – Madavara; Green Line complete
- 11 Aug 2025Yellow Line Yellow Line RV Road – Bommasandra (19.15 km); network about 96 km
- 14 Nov 2026nowPink Line Pink Line elevated Kalena Agrahara – SG Palya (7.5 km, 6 stations); inaugurated 13 Nov. Network 103.6 km
- Mar–May 2027targetPink Line Pink Line underground Dairy Circle – Nagawara (13.76 km, 12 stations)
- Mid-2027targetBlue Line Blue Line Central Silk Board – KR Puram (19.75 km)
- Sep 2027targetBlue Line Blue Line Hebbal – Airport (27.44 km)
- Early 2028targetBlue Line Blue Line KR Puram – Hebbal (11 km); full Blue Line by Mar 2028
- May 2031targetOrange Line Phase 3: Orange (32.15 km) and Grey (12.5 km) Lines; approved network about 222 km
- Not fixednot fixedRed Line Phase 3A Red Line Sarjapur – Hebbal, awaiting Union approval
- Not fixednot fixedPhase 4 Phase 4: 8 suburban corridors (about 215 km) at feasibility or DPR stage
Questions about upcoming lines
When will the Bengaluru Metro Blue Line to the airport open?
The Blue Line opens in stages. Targets: Silk Board to KR Puram: mid-2027 (about May 2027). Hebbal to Airport: Sep 2027. KR Puram to Hebbal: early 2028. Full line: Mar 2028 (targets). It runs 58.19 km from Central Silk Board to the airport with 30 stations.
When will the Pink Line underground section open?
The underground section from Dairy Circle to Nagawara (13.76 km, 12 stations) has a target of March to May 2027. The elevated section from Kalena Agrahara to SG Palya carries passengers from 6 am on 14 Nov 2026.
Which Bengaluru Metro lines are being built?
The Pink Line underground section and the Blue Line are under construction. The Orange and Grey Lines are approved with a May 2031 target. The Red Line is awaiting Union approval, and the Phase 4 corridors are proposals.
How long will the Bengaluru Metro network be?
From 14 Nov 2026 Namma Metro runs 103.6 km with 88 stations on the Purple, Green, Yellow and Pink Lines. When Phases 2 and 3 are complete the approved network will be about 222 km. Phase 4 proposals would add about 213 km more.